Planning FAQ

How long does planning permission take?

8 weeks statutory determination from validation. Plus 1-2 weeks validation. Plus 1-3 weeks design. Total: 12-14 weeks first-call to decision.

Architectural design tools and technical drawings — planning drawings in London
Short answer

A householder application must be determined within eight weeks of validation. Major development gets thirteen weeks, and larger home extension prior approval six. Add one to two weeks for validation, and four to eight more if the application is referred to planning committee.

Where does the time actually go?

Validation takes a few days to two weeks, and the eight-week clock only starts once the application is valid. Neighbour consultation runs 21 days from notification. The officer then assesses, consults internal specialists and writes the report, and the decision is issued — usually in weeks six to eight.

An incomplete submission is the commonest cause of delay: an application missing a heritage statement or carrying unscaled drawings simply sits until the item arrives, and the clock has not started.

What if the deadline passes?

You can appeal for non-determination, or agree an extension of time. In practice agreeing an extension is almost always better: a non-determination appeal takes the case away from an officer who may be close to approving and gives it to an inspector months later.

How long does the whole process take?

For a typical London extension: two to four weeks for survey and drawings, one to two weeks for validation, eight weeks for determination, then two to four weeks to discharge any pre-commencement conditions. Building regulations run in parallel, with a full plans application decided in five weeks.

Our drawing turnaround is 14 to 20 working days for the Essentials and loft packages and 20 to 28 for the Complete package.

Can it be sped up?

Not the statutory period, but the elapsed time can be shortened: submit a complete and accurate application, speak to the neighbours before the consultation letters land so objections do not trigger a committee referral, and run the building regulations submission alongside rather than after planning.

What does this mean for a London project?

How how long does planning permission take? plays out in Hackney: London Borough of Hackney (Hackney Council) maintains 29 conservation areas, the De Beauvoir Town Conservation Area and the Stoke Newington Conservation Area among them, and an Article 4 direction is in force there, so permitted development cannot be assumed. Anyone dealing with how long does planning permission take? at a Hackney address is therefore working to a £548 householder application decided in 8 weeks, or a £249 prior approval over 6 weeks where how long does planning permission take? still qualifies. are the Town and Country Planning Act 1990, the GPDO 2015 and the Building Regulations 2010.

Key figures

Key figures for How long does planning permission take?
Householder determination8 weeks
Major development13 weeks
Prior approval6 weeks
Neighbour consultation21 days
Full plans building control5 weeks
Our drawing turnaround14–20 working days

Related questions

When does the eight weeks start?

At validation, not at submission.

Does a committee referral add time?

Typically four to eight weeks, because the case must wait for a meeting date.

Can I start work while waiting?

Not on anything requiring the permission. Doing so risks enforcement.

A printed planning application drawing set — proposed elevations, floor plans and the os location plan with the site outlined in red — how long does planning permission take in London
The planning set that goes to the council through the Planning Portal: proposed elevations, plans, and the OS location plan with your site outlined.
Book a call

Speak to a chartered technologist — free 15 minutes

Pick a slot that suits you. No obligation and no sales pressure, just straight answers on your planning route.

How long does planning permission take? in London — a measured survey being recorded on site
A measured survey being recorded on site — how long does planning permission take? in London.

Found this useful? Share it

Copies the headline and the link, ready to paste anywhere — helpful if you are planning an extension with a neighbour, builder or architect.

Free quote in 60 seconds
Call us Free quote →

Before you go…

Get a free, no-obligation quote for your project. MCIAT chartered.

council-ready drawing review · All 33 London boroughs