Class A permitted development

Single storey extensions: when does planning permission apply?

Most single storey rear extensions on a house need no planning application if they stay within permitted development: 3m deep on a terrace or semi, 4m if detached, no higher than 4m, and eaves no higher than 3m within 2m of a boundary. Go past any limit, or build on a flat, and you need full permission.

Checked against the GPDO text on legislation.gov.uk (amendments to 9 April 2026) on 12 September 2026.

Single storey rear extension on a London terraced house

What can you build without planning permission?

A single storey extension to the rear or side of a house, inside the Class A limits in Schedule 2, Part 1 of the Town and Country Planning (General Permitted Development) (England) Order 2015.

Class A is the general right to enlarge a house. It does not list what you may build. It lists what you may not, and anything that avoids every exclusion is granted planning permission by the Order itself. For a single storey extension, these are the limits that decide it:

LimitTerraced or semi-detachedDetachedGPDO reference
Depth beyond the original rear wall3m4mA.1(f)(i)
Depth with prior approval (not on Article 2(3) land or an SSSI)6m8mA.1(g)(i)
Maximum height4m4mA.1(f)(ii)
Eaves height within 2m of a boundary3m3mA.1(i)
Side extension widthhalf the width of the original househalf the width of the original houseA.1(j)(iii)
Ground covered by extensions and outbuildings50% of the curtilage, excluding the original house50%A.1(b)

Source: GPDO 2015, Schedule 2, Part 1, Class A on legislation.gov.uk, retrieved 12 September 2026. The Planning Portal extensions guidance states the same limits.

Three more conditions sit alongside the table. The extension must not be taller than the highest part of the existing roof, its eaves must not be higher than the existing eaves, and exterior materials must look similar to the existing house. A verandah, balcony or raised platform takes the whole project out of Class A.

How is the 3m measured?

From the rear wall of the original house, which the Order treats as the house as it stood on 1 July 1948 or as first built if later.

This is where most London terraces trip up. A Victorian house with a two-storey back addition has an original rear wall at the back of that addition, so a 3m extension is measured from there. But if a previous owner added a kitchen in the 1980s, that kitchen already uses part of the allowance. Paragraph A.1(ja) adds the new work and any existing enlargement it joins together, and the total must still fit the limits.

Infilling a side return is a side extension in Class A terms, so it must stay single storey, under 4m high and no wider than half the original house. That half-width rule usually allows a side return infill on its own. Combine it with a deep rear extension and the pair is tested as one, which is why an L-shaped scheme is covered separately in our wraparound extension guide.

When does a single storey extension need full planning permission?

When it breaks any Class A limit, when the house has lost its permitted development rights, or when it is not a house at all.

  • Flats and maisonettes. Part 1 rights belong to dwellinghouses. A ground-floor flat extending into its garden always applies.
  • Houses created by a change of use. A.1(a) removes Class A where the home exists only by virtue of Classes G, M, MA, N, P, PA or Q of Part 3.
  • New-build estates. A.1(l) excludes houses built under Part 20, and many estate permissions carry a condition removing Class A.
  • Article 4 directions. A council can withdraw the right street by street. Check the Article 4 direction register before relying on it.
  • Forward of the principal elevation. Anything beyond the front wall, or a side wall facing a road, is excluded by A.1(e).
  • Article 2(3) land. In a conservation area, side extensions are not permitted at all, cladding is excluded, and the 6m or 8m prior approval route is unavailable.

Scope a single storey extension drawing package

Whether you end up with a certificate, a prior approval or a householder application, the drawings are the same core set: a measured survey, existing and proposed plans and elevations, and a building regulations package for the builder. The estimator gives an indicative design fee from the floor area.

Single storey rear extension with a flat roof and rooflights on a London house
A flat-roofed single storey rear extension, kept under 3m at the eaves where it meets the boundary.

What does each route cost and how long does it take?

A householder application costs £548 in England from 1 April 2026. A prior approval for a larger rear extension costs £249, and a certificate for a proposed extension costs half the full fee.

RouteCouncil fee from 1 April 2026Statutory periodWhen to use it
Nothing (within Class A)£0noneThe scheme fits every limit and rights are intact
Lawful development certificate (proposed)£274 (half of £548)no fixed statutory targetProof for a buyer's solicitor or a lender
Prior approval, larger home extension£24942 daysSingle storey rear extension 3m to 6m (4m to 8m detached)
Householder planning application£5488 weeksAnything outside Class A

Fees: MHCLG, Planning fees: annual indexation from 1 April 2026, which records a 3.8% rise, retrieved 12 September 2026. The 42-day period is in GPDO Class A paragraph A.4(10).

A householder application is less risky than people expect. In the year to March 2026, English councils decided 151,900 householder applications, 51% of all planning decisions, and granted 90% of them. They decided 93% within eight weeks or an agreed extension.

England, year to March 2026Figure
Householder decisions151,900
Share of all planning decisions51%
Householder applications granted90%
Decided within 8 weeks or agreed time93%

Source: MHCLG, Planning applications in England: January to March 2026, released 19 June 2026, retrieved 12 September 2026. These are national figures. London boroughs publish their own.

Should you rely on permitted development or apply anyway?

If the design fits comfortably inside the limits, build under Class A and get a certificate. It costs half the application fee, it is a legal determination rather than an opinion, and your buyer's solicitor will ask for it when you sell.

If the design needs the extra depth, compare two routes. Prior approval is cheaper and faster, but the council judges only the effect on neighbours, and an approval only covers what the Order allows. A householder application costs £548 and takes longer, but it can cover a roof lantern above 4m, a parapet on the boundary, or a side element Class A would exclude. When a design needs even one of those, apply for full permission from the start rather than re-drawing it after a refusal.

Planning is only half of it. Every habitable single storey extension needs building control approval for structure, insulation, drainage and fire safety, whichever planning route you take. If the wall is shared, the Party Wall etc. Act 1996 applies as well; our party wall guide for London covers the notices.

Written by Benyamen Shaukat, Technical Architect & Platform Founder. Fact-checked against GPDO Schedule 2, Part 1, Class A and the MHCLG fee schedule for 2026 to 2027.

Common questions

Is a 3m single storey extension always permitted development?

No. It must also stay under 4m high, keep its eaves under 3m within 2m of a boundary, avoid the front of the house, and the house must still have its Class A rights. Flats have none.

Can I build a 6m single storey extension without planning permission?

On a terraced or semi-detached house, yes, through the larger home extension prior approval route. It costs £249 and the council has 42 days. It is not available in conservation areas.

Does an existing kitchen extension count towards the 3m?

Yes. The depth is measured from the original rear wall, and paragraph A.1(ja) adds any existing enlargement the new work joins to the new work itself.

Do I need building regulations approval if I don't need planning permission?

Yes, for almost every habitable single storey extension. Planning and building regulations are separate. Conservatories and porches under 30 square metres can be exempt.

How much does a householder planning application cost in 2026?

£548 for one house in England from 1 April 2026, after a 3.8% indexation rise.

Construction drawings for a single storey extension laid out on site
Building regulations drawings on site. Planning and building control are separate approvals.

Where to go next

Which sources does this guide rely on?

Every limit, fee and statistic on this page was read from the primary source on 12 September 2026. Your council's Local Plan and any Article 4 direction can narrow the national rules.