Class A, paragraph A.4

Larger home extension prior approval, step by step

Larger home extension prior approval lets a single storey rear extension reach 6m on a terraced or semi-detached house, or 8m if detached, without a planning application. You send the council a description, a plan and neighbours' addresses with a £249 fee. Neighbours get at least 21 days to comment, and the council has 42 days to decide.

Checked against the GPDO text on legislation.gov.uk (amendments to 9 April 2026) on 12 September 2026.

Deep single storey rear extension on a London semi-detached house

What is larger home extension prior approval?

A notification procedure in paragraph A.4 of Class A that doubles the permitted depth of a single storey rear extension, subject to the council checking its effect on neighbours.

Ordinary Class A allows 3m, or 4m on a detached house. Paragraph A.1(g) raises that to 6m and 8m, and paragraph A.4 sets the conditions. It began as a temporary measure in 2013. Amendments in May 2019 removed its end date, so it is now a permanent part of the Town and Country Planning (General Permitted Development) (England) Order 2015.

RuleStandard Class AWith prior approvalReference
Depth, terraced or semi-detached3m6mA.1(f), A.1(g)
Depth, detached4m8mA.1(f), A.1(g)
Maximum height4m4mA.1(f)(ii), A.1(g)(ii)
Eaves within 2m of a boundary3m3mA.1(i)
StoreysoneoneA.1(g)
Article 2(3) land or SSSI3m and 4m limits applynot availableA.1(g)

Source: GPDO 2015, Schedule 2, Part 1, Class A, including the annotation omitting the time limit in A.1(g) from 25 May 2019, retrieved 12 September 2026.

What do you have to submit?

Paragraph A.4(2) sets out five items, plus the fee. Miss any of them and the council can refuse without assessing the scheme.

  1. A written description giving how far the extension projects beyond the original rear wall, its maximum height and its eaves height. If it joins an existing extension, the figures must cover both together.
  2. A plan showing the site, the proposal and any existing enlargement it joins.
  3. The addresses of all adjoining premises, including the properties behind the garden, not only the houses either side.
  4. Your contact address.
  5. Your email address, if you are content to receive the decision by email.

The fee for this prior approval in England is £249 from 1 April 2026. Most London boroughs accept the submission through the Planning Portal under the name 'prior approval: larger home extension'.

Fee: MHCLG, Planning fees: annual indexation from 1 April 2026, retrieved 12 September 2026.

Scope a prior approval drawing package

A prior approval needs less paperwork than a planning application, but the figures in it bind you. The build must match the depth, height and eaves you declared. The estimator gives an indicative fee for the drawings behind the submission and the building regulations set that follows.

Single storey rear extension six metres deep on a London house
A 6m single storey rear extension, the most a terraced or semi-detached house can reach through prior approval.

How does the 42-day process run?

The 42 days start when the council receives your information. Building work cannot start until one of three things happens.

StepWho actsTimeGPDO reference
1. Submission receivedCouncilday 0; the 42 days startA.4(2), A.4(10)(c)
2. Validity check; refusal possible if information is missing or the scheme breaks the limitsCouncilwithin the 42 daysA.4(3)
3. Notice served on every adjoining owner or occupierCouncilearly in the period; copy sent to youA.4(5), A.4(6)
4. Neighbours commentNeighboursat least 21 days from the notice date, public holidays excludedA.4(5)(d), A.4(16)
5. If anyone objects, the council assesses amenity on all adjoining premisesCouncilwithin the 42 daysA.4(7), A.4(9)
6. Decision: not required, granted (with or without conditions) or refusedCouncilby day 42A.4(10), A.4(12)

Source: GPDO 2015, Schedule 2, Part 1, paragraph A.4, retrieved 12 September 2026.

You may start work on receiving a notice that prior approval is not required, a notice granting it, or when 42 days pass without the council telling you either way. A.4(10)(c) says the silence must be a failure to notify you, so keep proof of when the council received the submission. The Planning Portal receipt is the simplest record.

Whatever the route, you must build what you described. Paragraph A.4(11) ties the work to the approved details, or to your submitted information if the approval was deemed. A deeper or taller extension than declared is unauthorised development.

What happens if a neighbour objects?

An objection does not stop the extension. It only makes the council assess the extension's effect on the amenity of adjoining premises.

This is a narrow test. The council cannot reopen design, materials or whether it likes flat roofs. It weighs overshadowing, loss of outlook, overbearing bulk and privacy, and paragraph A.4(9)(b) makes it consider all adjoining premises, including neighbours who did not write in. It can grant with conditions tied to amenity, such as obscure glazing on a side rooflight, under A.4(12).

In practice, London refusals turn on a 6m wall on the boundary of a terrace where the neighbour's rear window is close to it. Designing the eaves at the boundary well under 3m, stepping the height in from the party wall, or reducing the depth to 5m often changes the outcome. If the council refuses, you can appeal under section 78 of the Town and Country Planning Act 1990, or apply for full planning permission, where the council weighs the whole scheme.

Is prior approval better than a planning application?

For a plain single storey rear extension between 3m and 6m, usually yes. It costs £249 against £548 for a householder application, and it has a 42-day clock against eight weeks.

It is the wrong route when the design needs anything Class A does not allow: a side return element wider than half the house, a roof above 4m, a balcony or roof terrace, or a site in a conservation area. It also cannot be amended once submitted. Change a dimension and you start a new 42 days. If you are weighing the two routes in general rather than running this process, read full planning vs prior approval. For the standard limits, see the single storey extension planning guide.

Written by Benyamen Shaukat, Technical Architect & Platform Founder. Fact-checked against GPDO Schedule 2, Part 1, paragraphs A.1(g) and A.4, and the MHCLG fee schedule for 2026 to 2027.

Common questions

How long does larger home extension prior approval take?

The council has 42 days from receiving your information. If it has not told you whether prior approval is given or refused by then, you may build what you described.

How long do neighbours have to object?

At least 21 days from the date of the council's notice. Public holidays are not counted.

Can a neighbour stop a prior approval extension?

No. An objection only requires the council to assess the effect on neighbours' amenity. The council decides, and it must consider all adjoining premises.

Can I use prior approval in a conservation area?

No. The 6m and 8m limits do not apply on Article 2(3) land or a site of special scientific interest. You are limited to 3m or 4m, or a full application.

What is the fee for larger home extension prior approval?

£249 in England from 1 April 2026.

Do I still need building regulations approval?

Yes. Prior approval is a planning route only. The extension still needs building control approval.

Rear extension drawings used for a prior approval submission
The declared dimensions become the permission, so they are drawn from a measured survey, not estimated.

Where to go next

Which sources does this guide rely on?

The procedure below is taken from the text of the Order itself, read on 12 September 2026. Council validation lists can ask for more, such as elevations, but cannot change the 42-day period.

Found this useful? Share it

Copies the headline and the link, ready to paste anywhere — helpful if you are planning an extension with a neighbour, builder or architect.