Programme, not guesswork

How long does a house extension take?

From first sketch to finished room, a straightforward London extension typically runs six to nine months. Roughly half of that is approvals and procurement rather than building — and the approvals half is the part you can start today.

Last checked against current guidance on 2026-08-09. Rules differ by borough — the local pages below say how.

London terraced street — typical residential housing for house extensions

What does the whole programme look like?

StageTypical durationRuns in parallel with
Measured survey1–2 weeks from instruction
Design and planning drawings2–3 weeks
Council determination8 weeks from validation (42 days for prior approval)Building regulations design
Building regulations package2–4 weeks to produceCouncil determination
Structural calculations1–2 weeksBuilding regulations package
Party wall notices1–2 months' notice, plus award if dissentedCouncil determination
Tender and builder selection3–4 weeksBuilding regulations approval
Build (single-storey rear extension)12–16 weeks

Add the column of things that run in parallel and the honest total for a simple scheme is six to nine months, most of it before the first brick.

Which stage causes the most delay?

Validation, not determination. An application with missing or inaccurate drawings sits in the queue before the eight-week clock even starts.

Councils validate against a published local list — site plan at a recognised scale, existing and proposed elevations, correct fee, ownership certificate. Anything missing goes back, and the eight weeks restart from the day it is complete.

The second common delay is a survey that was never done: a design drawn from an estate agent's floor plan meets the real building at construction stage, and the redesign lands mid-programme.

Start the part that takes longest

Council determination is the long pole in this programme, and nothing shortens it except starting earlier with a complete submission. The estimator below scopes the drawing package your project needs, so you know what stage one involves.

Estimate your drawing costs

Move the controls for an indicative figure. It anchors your budget — it is not a quote. Every project is priced after a free survey.

1 · Project type
2 · Approximate size
30
3 · Add compliance packages
Indicative design fee £1,585
Book your free feasibility call

Build costs are separate and quoted by your contractor. See our published fees.

How long does a house extension take? in London — a flat-roof rear extension with rooflights
A flat-roof rear extension with rooflights — how long does a house extension take? in London.

What can you start before planning is decided?

  • The building regulations package, where the scheme is low planning risk.
  • Party wall notices — the two-month clock is best spent during determination.
  • The drainage and water enquiry, and any build over agreement.
  • Builder conversations and early availability checks; good builders book out months ahead.

What you should not start is anything a planning change would waste — bespoke joinery, glazing orders, or a full tender on drawings that may move.

How long does the build itself take?

A single-storey rear extension of typical London size is commonly twelve to sixteen weeks on site, longer where the ground is poor, access is through the house, or the scheme includes a large structural opening.

Loft conversions run to a similar timescale; wraparounds and two-storey extensions longer, because there is more structure and more weathering to sequence.

What happens if planning is refused?

You can amend and resubmit — usually free within twelve months on the same site — or appeal, which for householder cases uses the faster householder appeal service.

Resubmission is almost always quicker than appeal, and the officer's report tells you exactly what to change. Appeals are worth it where the refusal turns on a point of principle rather than a fixable design detail.

Either way the delay is measured in months, which is the strongest argument for resolving daylight, roofline and neighbour issues on the drawing board.

Written by Benyamen Shaukat, Technical Architect & Platform Founder. Fact-checked against statutory determination periods for householder applications and prior approval.

Common questions

How long does the council take to decide?

Eight weeks from validation for a householder application, and 42 days for prior approval on a larger home extension. Validation itself can add one to two weeks.

Can building work start before building regulations approval?

Work can start under a building notice with 48 hours' notice, but on anything structural a full plans application checked in advance is the safer route.

How far ahead should I book a builder?

Good London builders are commonly booked three to six months out. Start the conversation during determination, not after approval.

Does a lawful development certificate take as long as planning permission?

Councils aim for eight weeks on both. The certificate is decided on law and fact rather than planning merit, so a complete, accurate submission matters more than a persuasive one.

What is the single biggest time saver?

An accurate measured survey at the start. Almost every mid-project delay traces back to the building not matching the drawing.

How long does a house extension take? in London — a two-storey extension with a balcony
A two-storey extension with a balcony — how long does a house extension take? in London.

Where to go next

What sets each deadline

Most of the waiting on an extension is statutory rather than discretionary — the determination period, the consultation window and the building control decision are all fixed in regulation. Where a Local Plan requires pre-application engagement, or CIL is chargeable on the additional floor area, add that to the front of the programme: