Part F: the ventilation London building work must provide

Ventilation. Background and purge ventilation requirements.

London terraced street — typical residential housing for architectural drawings in London
In short

Approved Document F sets ventilation requirements for dwellings — background ventilation, extract from wet rooms and purge ventilation. The 2021 edition raised the standards significantly, requiring larger trickle ventilators and, where windows are replaced, ventilation at least equivalent to what was there before.

What extract rates does Part F actually require?

Intermittent extract of 30 litres per second in a kitchen with a cooker hood, 60 without one, 15 in a bathroom and 6 in a WC. Purge ventilation needs an openable area of at least one twentieth of the floor it serves.

RoomIntermittent extract rateNotes
Kitchen, hood over the hob30 l/s
Kitchen, elsewhere in the room60 l/s
Utility room30 l/s
Bathroom15 l/swith or without a WC
Sanitary accommodation6 l/sor 4 air changes per hour
Purge ventilation, any roomopenable area ≥ 1/20 of floor areahinged or pivot windows ≥ 30°

Source: Approved Document F, Volume 1: Dwellings (2021 edition), Tables 1.1 and 1.3, read at 1 September 2026. Part F bites on a London extension whenever the work covers over an existing window or removes a room’s ventilation route — a rear extension across a kitchen window is the commonest trigger, and it is checked by building control rather than by planning.

What are the extract rates?

Intermittent extract: 30 l/s in a kitchen if above a hob, or 60 l/s elsewhere in the kitchen; 15 l/s in a utility room; 6 l/s in a bathroom; 6 l/s in a WC. Continuous extract runs lower — 13 l/s kitchen, 8 l/s bathroom, 6 l/s WC — with a boost rate above.

Purge ventilation must be provided in every habitable room, normally by an openable window with an opening area of at least one twentieth of the floor area.

What changed for window replacement?

The 2021 edition requires that replacement windows provide background ventilation no worse than the windows they replace, and where the existing windows had trickle ventilators, the new ones must too. The recommended equivalent area for a habitable room in an existing dwelling is 8,000 mm² per room.

This is the single most commonly missed requirement in London window replacement projects, and it is a building regulations breach that surfaces on sale.

How does it interact with airtightness?

Tightening the fabric without matching ventilation causes condensation and mould. Approved Document F is designed to be read with Part L: as air permeability falls, the ventilation system has to take over from adventitious leakage.

What does approved document f (ventilation) mean for a London project?

A worked Ealing example of approved document f (ventilation): with 30 conservation areas — the Ealing Broadway Conservation Area and the Pitshanger Conservation Area among the best known — London Borough of Ealing (Ealing Council) sees approved document f (ventilation) constantly, and an Article 4 direction is in force there, so permitted development cannot be assumed. Where approved document f (ventilation) pushes a Ealing scheme out of permitted development, the route becomes a £548 application decided in 8 weeks rather than a £249 prior approval in 6 weeks.

Approved Document F (ventilation) at a glance

Key figures for Approved Document F (ventilation)
Kitchen extract, over hob30 l/s intermittent
Kitchen extract, elsewhere60 l/s intermittent
Bathroom extract15 l/s intermittent, 8 l/s continuous
WC extract6 l/s
Purge ventilation1/20 of floor area openable
Trickle vent, habitable room8,000 mm² equivalent area

Common questions about approved document f (ventilation)

Do replacement windows need trickle vents?

Yes, where the existing windows had them, and ventilation must not be reduced.

Is an extractor hood enough for a kitchen?

Only if it extracts to outside at the required rate — recirculating hoods do not count.

Does a loft conversion need extra ventilation?

Each new habitable room needs background and purge ventilation.

An architectural technologist checking a printed set of house drawings, marking a proposed elevation in red — part f (building regs) in London
Every set is checked line by line against the validation checklist before it leaves the office.
Book a call

Speak to a chartered technologist — free 15 minutes

Pick a slot that suits you. No obligation and no sales pressure, just straight answers on your planning route.

Need help with Part F (Building Regs)?

Talk to our MCIAT teamOr contact us about your project first
Part F (Building Regs) in London — a London terraced street of the type we survey
A london terraced street of the type we survey — part f (building regs) in London.

Found this useful? Share it

Copies the headline and the link, ready to paste anywhere — helpful if you are planning an extension with a neighbour, builder or architect.

Free quote in 60 seconds
Call us Free quote →

Before you go…

Get a free, no-obligation quote for your project. MCIAT chartered.

council-ready drawing review · All 33 London boroughs