In England a full planning permission is valid for three years from the date on the decision notice, unless the council sets a different period. You do not have to finish in that time. You have to begin, with a lawful "material operation" such as digging a foundation trench, after every pre-commencement condition has been discharged.
Checked against legislation.gov.uk and GOV.UK guidance on 12 September 2026. Your borough applies these rules through its own Local Plan.
Section 91 of the Town and Country Planning Act 1990 makes every planning permission subject to a condition that the development "must be begun" before the applicable period runs out. In England that period is 3 years from the grant.
Your decision notice will normally repeat this as its first condition. If a council forgets to include it, the Act fills the gap: the permission is deemed to carry the same three-year condition anyway. The clock starts on the date of the grant printed on the notice, not the day you received it or the day the neighbours stopped objecting.
This page is about how long a permission lasts once you have it. How long a council takes to decide an application is a different question, covered in our guide to how long planning permission takes.
| Type of consent | Deadline | Legal basis |
|---|---|---|
| Full or householder planning permission, England | Begin within 3 years of the grant | s91 |
| Full planning permission, Wales | Begin within 5 years of the grant | s91 |
| Outline permission: reserved matters | Apply within 3 years of the outline grant | s92 |
| Outline permission: start on site, England | Begin within 2 years of final approval of reserved matters | s92 |
| Permission granted by a development order (permitted development) | Not subject to the s91 deadline | s91 exceptions |
| Extending the deadline with a section 73 application | Not allowed in England | s73(5) |
Sources: Town and Country Planning Act 1990, section 91, section 92 and section 73, legislation.gov.uk, retrieved 12 September 2026.
Development begins on the earliest date a "material operation" comprised in the development is carried out. Section 56(4) lists what qualifies.
| Material operation under s56(4) | Typical householder example |
|---|---|
| Any work of construction in the course of erecting a building | Laying the first course of blockwork for the extension |
| Any work of demolition of a building | Taking down the existing outrigger the permission replaces |
| Digging a trench to contain the foundations, or part of them | Excavating a foundation trench on the approved footprint |
| Laying an underground main or pipe to the foundations | A drainage run serving the new extension |
| Laying out or constructing a road, or part of one | Rarely relevant to a house |
| A change of use that is material development | Starting to use a building for the permitted use |
Source: Town and Country Planning Act 1990, section 56(4), legislation.gov.uk, retrieved 12 September 2026.
Two words carry the weight: "comprised in". The operation has to be part of the approved scheme. A trench dug in the wrong place, or a clearance of the garden that is not in the drawings, does not start the permission. The bar is low, but the work has to be yours to point at: in the right position, on the approved plans, and recorded.
Because work that breaches a condition is unlawful. If the three years then run out, you may hold an expired permission and a partly built extension.
A pre-commencement condition says something must be approved "before development commences". On London householder schemes that is typically a materials sample, a construction management plan on a tight street, a tree protection plan, or a basement impact assessment detail. The government guidance at paragraph 007 is plain: development carried out without complying with a condition "would be unlawful and may be the subject of enforcement action."
The practical risk is timing. Owners dig a trench in month 35 to "save" the permission, not realising a condition is still undischarged. Whether that trench counts as a lawful start is exactly what the council will dispute later. The safe sequence is to discharge first, then start.
| Pre-commencement rule | Figure |
|---|---|
| Council needs your written agreement to impose one | Yes, section 100ZA, with limited exceptions |
| Time to reply to the council's notice proposing one | 10 working days from the day after the notice |
| Decision period for discharging a condition | 8 weeks (16 weeks for EIA development) |
| Fee refunded if not decided within | 12 weeks |
| Discharge fee, householder development | £89 |
| Discharge fee, any other case | £309 |
| Certificate of lawfulness for an existing operation, householder | £548 (same as the full application fee) |
| Fresh householder application if the permission lapses | £548 |
Sources: MHCLG, Use of planning conditions (paragraphs 007, 034, 036); Town and Country Planning (Pre-commencement Conditions) Regulations 2018, regulation 2; Planning fees from 1 April 2026. All retrieved 12 September 2026.
Count backwards. Eight weeks for each discharge application, plus time to prepare the details, plus a margin in case the council asks for more. With a condition to discharge, aim to submit the details no later than month 30.
Keep evidence as you go. If the question is ever disputed, apply for a certificate of lawfulness for the existing operation.
A lawful development certificate for an existing operation costs the same as a full application: £548 for a householder scheme from 1 April 2026. It matters most when you plan to sell a house with a started but unfinished permission. A buyer's solicitor will want to see that the permission is still alive. Our fee for preparing an LDC is £556 to £1,050, set out on our pricing page.
Section 91 sets a date to begin, not a date to finish. A lawfully begun householder permission does not lapse under section 91 because the build is slow.
That does not make a stalled site risk-free. The practical limits sit in other regimes. Building regulations approval, party wall awards and CIL exemptions each run on their own rules, and a long-stalled site can lose them even while the planning permission survives.
You cannot buy more time through a section 73 application: subsection (5) forbids extending the start date in England, and the government guidance repeats it at paragraph 014. That leaves three honest routes:
Our Essentials package, from £840, covers the drawings and submission for a fresh householder application. It includes a free resubmission if the application is refused. You can ask for a quote with your decision notice to hand.
Three years from the date of the grant, under section 91 of the Town and Country Planning Act 1990, unless the decision notice sets a different period. Wales uses five years.
No. You have to begin. Once a material operation, such as digging a foundation trench, is lawfully carried out, the section 91 deadline has been met.
Not in England through a section 73 application, which cannot extend the start date. You either begin lawfully before the deadline or apply again.
Section 56(4) lists demolition of a building as a material operation, but only where the demolition is part of the approved development and all pre-commencement conditions are discharged.
Reserved matters must be applied for within 3 years of the outline grant, and in England development must begin within 2 years of final approval of the reserved matters.
Every figure on this page comes from the documents below, retrieved on 12 September 2026. Read your own decision notice alongside them: its conditions are what bind your site.