After the decision notice: conditions and deadlines

How long is planning permission valid, and what counts as starting?

In England a full planning permission is valid for three years from the date on the decision notice, unless the council sets a different period. You do not have to finish in that time. You have to begin, with a lawful "material operation" such as digging a foundation trench, after every pre-commencement condition has been discharged.

Checked against legislation.gov.uk and GOV.UK guidance on 12 September 2026. Your borough applies these rules through its own Local Plan.

A double-storey rear extension on a London house, built after its planning permission was lawfully begun

What does the three-year rule actually say?

Section 91 of the Town and Country Planning Act 1990 makes every planning permission subject to a condition that the development "must be begun" before the applicable period runs out. In England that period is 3 years from the grant.

Your decision notice will normally repeat this as its first condition. If a council forgets to include it, the Act fills the gap: the permission is deemed to carry the same three-year condition anyway. The clock starts on the date of the grant printed on the notice, not the day you received it or the day the neighbours stopped objecting.

This page is about how long a permission lasts once you have it. How long a council takes to decide an application is a different question, covered in our guide to how long planning permission takes.

Type of consentDeadlineLegal basis
Full or householder planning permission, EnglandBegin within 3 years of the grants91
Full planning permission, WalesBegin within 5 years of the grants91
Outline permission: reserved mattersApply within 3 years of the outline grants92
Outline permission: start on site, EnglandBegin within 2 years of final approval of reserved matterss92
Permission granted by a development order (permitted development)Not subject to the s91 deadlines91 exceptions
Extending the deadline with a section 73 applicationNot allowed in Englands73(5)

Sources: Town and Country Planning Act 1990, section 91, section 92 and section 73, legislation.gov.uk, retrieved 12 September 2026.

What counts as starting work?

Development begins on the earliest date a "material operation" comprised in the development is carried out. Section 56(4) lists what qualifies.

Material operation under s56(4)Typical householder example
Any work of construction in the course of erecting a buildingLaying the first course of blockwork for the extension
Any work of demolition of a buildingTaking down the existing outrigger the permission replaces
Digging a trench to contain the foundations, or part of themExcavating a foundation trench on the approved footprint
Laying an underground main or pipe to the foundationsA drainage run serving the new extension
Laying out or constructing a road, or part of oneRarely relevant to a house
A change of use that is material developmentStarting to use a building for the permitted use

Source: Town and Country Planning Act 1990, section 56(4), legislation.gov.uk, retrieved 12 September 2026.

Two words carry the weight: "comprised in". The operation has to be part of the approved scheme. A trench dug in the wrong place, or a clearance of the garden that is not in the drawings, does not start the permission. The bar is low, but the work has to be yours to point at: in the right position, on the approved plans, and recorded.

Why can a pre-commencement condition cost you the permission?

Because work that breaches a condition is unlawful. If the three years then run out, you may hold an expired permission and a partly built extension.

A pre-commencement condition says something must be approved "before development commences". On London householder schemes that is typically a materials sample, a construction management plan on a tight street, a tree protection plan, or a basement impact assessment detail. The government guidance at paragraph 007 is plain: development carried out without complying with a condition "would be unlawful and may be the subject of enforcement action."

The practical risk is timing. Owners dig a trench in month 35 to "save" the permission, not realising a condition is still undischarged. Whether that trench counts as a lawful start is exactly what the council will dispute later. The safe sequence is to discharge first, then start.

Pre-commencement ruleFigure
Council needs your written agreement to impose oneYes, section 100ZA, with limited exceptions
Time to reply to the council's notice proposing one10 working days from the day after the notice
Decision period for discharging a condition8 weeks (16 weeks for EIA development)
Fee refunded if not decided within12 weeks
Discharge fee, householder development£89
Discharge fee, any other case£309
Certificate of lawfulness for an existing operation, householder£548 (same as the full application fee)
Fresh householder application if the permission lapses£548

Sources: MHCLG, Use of planning conditions (paragraphs 007, 034, 036); Town and Country Planning (Pre-commencement Conditions) Regulations 2018, regulation 2; Planning fees from 1 April 2026. All retrieved 12 September 2026.

Count backwards. Eight weeks for each discharge application, plus time to prepare the details, plus a margin in case the council asks for more. With a condition to discharge, aim to submit the details no later than month 30.

How do you prove the permission was lawfully started?

Keep evidence as you go. If the question is ever disputed, apply for a certificate of lawfulness for the existing operation.

  • The council's letters confirming each pre-commencement condition is discharged, with dates.
  • Dated photographs of the material operation, taken wide enough to show its position on the site.
  • A building control commencement record or inspection of the excavation.
  • Invoices from the groundworker naming the address and the work.
  • If the scheme is liable for the Community Infrastructure Levy, or relies on an exemption, the Form 6 commencement notice served before starting.

A lawful development certificate for an existing operation costs the same as a full application: £548 for a householder scheme from 1 April 2026. It matters most when you plan to sell a house with a started but unfinished permission. A buyer's solicitor will want to see that the permission is still alive. Our fee for preparing an LDC is £556 to £1,050, set out on our pricing page.

Once started, is there a deadline to finish?

Section 91 sets a date to begin, not a date to finish. A lawfully begun householder permission does not lapse under section 91 because the build is slow.

That does not make a stalled site risk-free. The practical limits sit in other regimes. Building regulations approval, party wall awards and CIL exemptions each run on their own rules, and a long-stalled site can lose them even while the planning permission survives.

What if your permission is about to expire?

You cannot buy more time through a section 73 application: subsection (5) forbids extending the start date in England, and the government guidance repeats it at paragraph 014. That leaves three honest routes:

  1. Start lawfully before the date. Discharge conditions, then carry out a material operation on the approved footprint.
  2. Apply again. A new householder application costs £548. Policy may have changed since the first grant, so check the current Local Plan before assuming the same answer.
  3. Let it lapse if the design is no longer right, and apply for what you now want. If the changes are small, amending an existing permission may still be possible while it is live.

Our Essentials package, from £840, covers the drawings and submission for a fresh householder application. It includes a free resubmission if the application is refused. You can ask for a quote with your decision notice to hand.

Written by Benyamen Shaukat, Technical Architect & Platform Founder. Fact-checked against sections 56, 73, 91 and 92 of the Town and Country Planning Act 1990 and the planning conditions guidance, 12 September 2026.

Common questions

How long is planning permission valid for in England?

Three years from the date of the grant, under section 91 of the Town and Country Planning Act 1990, unless the decision notice sets a different period. Wales uses five years.

Do I have to finish the building within three years?

No. You have to begin. Once a material operation, such as digging a foundation trench, is lawfully carried out, the section 91 deadline has been met.

Can I extend planning permission before it expires?

Not in England through a section 73 application, which cannot extend the start date. You either begin lawfully before the deadline or apply again.

Does demolition count as starting the permission?

Section 56(4) lists demolition of a building as a material operation, but only where the demolition is part of the approved development and all pre-commencement conditions are discharged.

How long does outline planning permission last?

Reserved matters must be applied for within 3 years of the outline grant, and in England development must begin within 2 years of final approval of the reserved matters.

Where to go next

The law behind the deadline

Every figure on this page comes from the documents below, retrieved on 12 September 2026. Read your own decision notice alongside them: its conditions are what bind your site.