Changing an approved scheme: variation of condition

Amending planning permission: which route fits your change?

There are three routes. A small change that does not alter the substance of the permission goes through a non-material amendment under section 96A, costing £46 for householder schemes and decided within 28 days. A bigger change within the same description goes through section 73, at £89. Anything that changes what the development is needs a fresh application.

Checked against legislation.gov.uk and GOV.UK guidance on 12 September 2026. Your borough applies these rules through its own Local Plan.

A double-storey rear extension on a London house, the kind of approved scheme owners often need to amend

What are the routes for changing an approved scheme?

Non-material amendment, minor material amendment through section 73, or a new planning application. They differ in cost, speed, consultation and whether you can appeal.

Almost every approved extension changes between the decision notice and the finished building. The structural engineer moves a steel, the builder proposes a cheaper window, or a neighbour's party wall surveyor asks for a lower parapet. What matters is picking the right route before the change is built. Work that departs from the approved drawings is a breach, whatever the route you later choose.

Non-material amendment (s96A)Section 73 applicationNew application
Use it forChanges that do not alter the substance of the permissionMaterial changes, made by varying or removing a condition such as the approved-plans conditionChanges to the description of development, or anything s73 cannot do
Householder fee£46£89£548
Fee, other non-major cases£309£608Depends on category
Fee, major development£309£2,076Depends on category
Decision period28 days, unless extended in writing8 weeks for non-major applications8 weeks for non-major applications
Notice to other ownersBefore applying, with 14 days to make representationsOwnership certificate, as for an applicationOwnership certificate
Statutory publicityDoes not apply; council has discretionYesYes
Right of appealNoneYesYes
ResultThe original permission, changedA new, independent permission alongside the originalA new permission

Source: MHCLG, Fees for planning applications in England from 1 April 2026, retrieved 12 September 2026. Procedure: Flexible options for planning permissions and Determining a planning application (paragraph 001), retrieved 12 September 2026.

What counts as a non-material amendment?

There is no statutory definition. The council decides whether a change is non-material in the context of the whole scheme, and must weigh it together with any earlier amendments.

The government guidance says so at paragraph 002, and section 96A(2) adds the part owners miss: the council has to consider the effect of the change together with any previous changes made under the section. Three small amendments can add up to one material one. On a London terrace, officers ask a simple question: would a neighbour who commented on the original scheme see this change as different? If yes, it is probably material.

Changes that councils commonly accept as non-material on householder schemes:

  • A rooflight moved along the same roof slope, or reduced in size.
  • A window or door moved slightly on an elevation that faces your own garden.
  • A like-for-like material swap where the approved drawings named a specific product.
  • A small reduction in the footprint, height or depth of the extension.

Changes that are usually material:

  • Any increase in height, depth or width, however small, at a shared boundary.
  • A new window facing a neighbour, or a flat roof becoming a terrace.
  • A different roof form, such as a pitched roof replaced with a flat one next to a listed or locally listed building.
  • A change in materials in a conservation area where the approved material was part of the reason for approval.

How does a section 73 application work?

You apply to carry out the development without complying with a condition, or with a varied one. The council considers only the conditions, and grants a new permission if it agrees.

Most approved extensions carry a condition listing the approved drawings by number. A section 73 application to vary that condition, substituting revised drawings, is how a "minor material amendment" is made. Section 73(2) confines the council to the question of the conditions, so it cannot reopen the principle of the extension. It will still judge the revised design against current policy.

Section 73 limitWhat it means for you
Takes effect as a new, independent permissionThe original still exists. Your builder must work to one or the other, not a mix
Cannot change the description of developmentA single-storey rear extension cannot become a two-storey one through s73
Cannot extend the time to begin developmentSection 73(5) bars it in England. The start date stays tied to the original grant
Publicity appliesNeighbours are notified again and can comment for at least 21 days
Conditions carry over only if restatedCheck that the new decision notice repeats every condition that still applies, including those already discharged

Sources: MHCLG, Flexible options for planning permissions (paragraphs 002 to 015); Town and Country Planning Act 1990, section 96A and section 73. All retrieved 12 September 2026. Publicity: Consultation and pre-decision matters, retrieved 12 September 2026.

Check the new decision notice line by line. If a condition you had already discharged is restated without reference to the approved details, you may have to discharge it again, at £89 for a householder scheme.

Who can apply for a non-material amendment, and do neighbours get a say?

Only someone with an interest in the land. Before applying, you must notify any other owner and give them 14 days to comment. Neighbours are not formally consulted, though the council may choose to ask them.

The Development Management Procedure Order publicity rules do not apply to section 96A applications (paragraph 005), so no site notice or letters are required. That is why the route is quick. It is also why officers refuse anything a neighbour might reasonably have wanted to comment on. Where they are unsure, they tend to say no, and a refused non-material amendment carries no appeal. The usual next step is a section 73 application, with its fee and timescale.

A non-material amendment also cannot be used on a listed building consent (paragraph 004). If your house is listed, amendments to the listed building consent need their own route.

When is a fresh application the better choice?

Choose a new application when the change alters the description, when the permission is close to its three-year start deadline and you need more time, or when several amendments have stacked up. A clean new permission with one set of drawings is also easier for a buyer's solicitor to follow than an original grant with a trail of amendments.

Time matters too. A £46 amendment decided in 28 days is the cheapest route when it fits. If an officer has already warned you the change looks material, applying for an amendment first can cost a month for nothing. Ask the case officer informally before you choose. Some councils will give a view by email on a marked-up drawing. Where the scheme needs wider rethinking, pre-application advice is the more reliable way to test it.

What should an amendment submission include?

  1. A covering letter naming the permission reference, the condition affected, and each change in one sentence.
  2. Revised drawings with a revision letter, the change clouded, and superseded drawing numbers listed.
  3. A comparison of approved and proposed elevations side by side where height or openings change.
  4. The ownership notice for a section 96A application where others own part of the land.
  5. The right fee: £46 or £89 for householder schemes from 1 April 2026.

We prepare revised drawings and the covering letter for amendments to schemes we drew and to schemes drawn by others. Planning drawings on their own start from £840, as listed on our pricing page. For a small amendment, ask for a quote with the decision notice and approved drawings attached.

Written by Benyamen Shaukat, Technical Architect & Platform Founder. Fact-checked against sections 73 and 96A of the Town and Country Planning Act 1990, the flexible options guidance and the 2026 fee schedule, 12 September 2026.

Common questions

How much does a non-material amendment cost?

From 1 April 2026 the fee is £46 where the application relates to householder development and £309 in any other case.

How long does a non-material amendment take?

The council must decide within 28 days, or a longer period agreed in writing. There is no statutory neighbour publicity, which is why it is quicker than a section 73 application.

Can I appeal a refused non-material amendment?

No. Section 96A applications fall outside the section 78 right of appeal. The usual alternative is a section 73 application, which does carry appeal rights.

Does a section 73 application give me more time to start?

No. Section 73(5) prevents a section 73 permission from extending the time within which development must be begun in England.

Can I build the changes while the amendment is being decided?

It is a risk. Until the amendment is approved, anything that departs from the approved drawings is a breach the council can take enforcement action against.

Where to go next

The law behind each amendment route

Every figure on this page comes from the documents below, retrieved on 12 September 2026. Your council's own validation checklist sets what it wants submitted with each route.