A porch on a house needs no planning permission if its ground area measured externally is 3 square metres or less, no part is over 3m above ground level, and no part is within 2m of a boundary with a road. Break any one of these, or build on a flat, and you need a householder application.
Checked against the GPDO text on legislation.gov.uk (amendments to 9 April 2026) on 12 September 2026.
Not if it fits Class D of Schedule 2, Part 1 of the Town and Country Planning (General Permitted Development) (England) Order 2015. That class covers a porch outside any external door of a house.
| Class D limit | Figure | Reference |
|---|---|---|
| Ground area, measured externally | 3 square metres or less | D.1(b) |
| Height of any part above ground level | 3m or less | D.1(c) |
| Distance from a boundary with a highway | 2m or more | D.1(d) |
| House created by a Part 3 change of use (Classes G, M, MA, N, P, PA, Q) | not permitted | D.1(a) |
| House built under Part 20 (new dwellinghouses) | not permitted | D.1(e) |
Source: GPDO 2015, Schedule 2, Part 1, Class D on legislation.gov.uk, retrieved 12 September 2026. The Planning Portal porch guidance gives the same three limits.
Class D applies to a porch outside any external door, front, side or back. A porch over a back door is often easier to fit into the general Class A rules for extensions, but most people asking this question are thinking of the front door, where Class D is the only permitted development route.
On the ground, to the outside face of the walls. Roof overhang does not count, but wall thickness does.
A brick porch with 100mm walls that looks like 1.5m by 2m inside can measure about 1.7m by 2.1m outside, or 3.57 square metres. That breaks Class D. Draw the porch to the outside of the brickwork first and fit the internal space to what is left.
| External size | Ground area | Within 3 square metres? |
|---|---|---|
| 1.5m x 2.0m | 3.00 square metres | yes, exactly on the limit |
| 1.2m x 2.4m | 2.88 square metres | yes |
| 1.7m x 2.1m | 3.57 square metres | no |
| 1.0m x 3.2m | 3.20 square metres | no |
Height is measured from ground level to the highest part of the structure, including a pitched roof's ridge. A gabled porch that looks right against a two-storey Victorian front often reaches 3m at the apex, so a lower pitch or a lean-to roof is the usual fix.
Whenever the front garden is shallow. The distance runs from the nearest part of the porch to the boundary with the road, and in the Order a highway includes the footway.
Many inner London terraces have front gardens of 2m to 3m. Once a porch projects more than a metre from the front wall, it is often within 2m of the front boundary and outside Class D. Houses on a corner plot have a second highway boundary at the side, which can catch a side-door porch too.
A porch that fails Class D cannot fall back on Class A. Paragraph A.1(e) excludes any extension beyond the principal elevation, so a front porch outside the three limits needs a householder planning application.


A porch inside Class D needs no drawings for planning, although a certificate needs a plan. A larger porch, or one on a flat, needs a householder set: survey, existing and proposed elevations, and a site plan. The estimator's smallest settings give an indicative fee.

You apply for householder planning permission. In England that costs £548 for one house from 1 April 2026.
| Route | Council fee | Typical time |
|---|---|---|
| Within Class D, no application | £0 | none |
| Lawful development certificate (proposed) | £274, half the application fee | no fixed statutory target |
| Householder planning application | £548 | 8 weeks target |
Fees: MHCLG, Planning fees: annual indexation from 1 April 2026, retrieved 12 September 2026. Decision target: MHCLG, Planning applications in England: January to March 2026.
Councils granted 90% of the 151,900 householder applications decided in England in the year to March 2026. A porch is rarely contentious, but on a uniform Victorian or Edwardian terrace a design that breaks a repeated front elevation is the most common reason for refusal. Matching the brick, keeping the roof below the first-floor window sills, and following any porches already on the street are the safest choices.
Flats and maisonettes have no Part 1 permitted development rights, so any porch on a block of flats needs permission. An Article 4 direction or a planning condition can also remove Class D from a house. Class D is not withdrawn simply because a house is in a conservation area, but many London conservation areas carry Article 4 directions covering front elevations, so check the conservation area planning guide and your council's register.
Usually not. Class 7 of Schedule 2 to the Building Regulations 2010 exempts a porch added at ground level with a floor area of 30 square metres or less.
The exemption comes with a condition: any glazing must meet the safety glazing requirements in Part K. Two things take a porch outside the exemption. Removing the existing front door and opening the hall into the porch makes it part of the house, and a new WC or radiator connected to the house system brings in the drainage and energy rules.
| Building regulations test | Figure or rule | Source |
|---|---|---|
| Position | added at ground level | BR 2010 Sch. 2, Class 7 |
| Floor area | 30 square metres or less | BR 2010 Sch. 2, Class 7 |
| Glazing | must meet Part K safety glazing requirements | BR 2010 Sch. 2, Class 7 |
Source: The Building Regulations 2010, Schedule 2 on legislation.gov.uk, retrieved 12 September 2026.
Up to 3 square metres of ground area measured externally, no more than 3m high at any point, and at least 2m from any boundary with a road.
Class D itself is not withdrawn in conservation areas, but an Article 4 direction often is. Check your council's register before you build.
Yes. Permitted development rights for porches apply only to houses.
Usually not, if it is at ground level, under 30 square metres and its glazing meets Part K. Removing the front door between the porch and the house changes that.
£548 for a householder application in England from 1 April 2026, or £274 for a certificate confirming a porch is lawful.

The three porch limits, the building regulations exemption and the fees were read from the primary sources on 12 September 2026.