Foundations using piles driven into deeper, stronger strata. Common for basements and large extensions in soft ground.
A piled foundation transfers load to deeper, stronger ground through columns bored or driven into the soil. In London domestic work piles are used where trees, shrinkable London Clay, poor made ground or an adjacent basement make a traditional strip footing impractical.
The usual triggers are a mature tree within influencing distance on shrinkable clay, where NHBC guidance would demand a strip foundation 2.5 m deep or more; deep made ground; a high water table; or a neighbour's basement that a conventional footing would undermine.
London Clay is highly shrinkable, and desiccation from a nearby oak, willow or poplar reaches far further than most owners expect. The tree survey and the foundation design are therefore the same conversation.
Mini piles — typically 150 to 300 mm diameter, bored with a restricted-access rig and reinforced — are the domestic norm because they fit through a house. They are capped with a reinforced concrete ground beam that spans between them and carries the wall.
Screw or helical piles are used where vibration and spoil must be minimised, and are quick where ground conditions suit.
Piling typically costs more than a strip footing on a small extension but less than a very deep mass-fill trench. Because piles usually sit within your own boundary, they can also avoid the oversail a wide strip footing would cause — though excavation within 3 m of a neighbouring structure still triggers a section 6 party wall notice with two months' notice.
A worked Hounslow example of piled foundation: with 30 conservation areas — the Chiswick Conservation Area and the Bedford Park Conservation Area among the best known — London Borough of Hounslow (Hounslow Council) sees piled foundation constantly, and there is no borough-wide Article 4 direction, so permitted development generally survives outside conservation areas. Where piled foundation pushes a Hounslow scheme out of permitted development, the route becomes a £548 application decided in 8 weeks rather than a £249 prior approval in 6 weeks.
| Typical mini pile diameter | 150–300 mm |
|---|---|
| Capped with | Reinforced concrete ground beam |
| Common trigger | Trees on shrinkable London Clay |
| Alternative | Deep mass-fill trench or raft |
| Party wall notice | Two months, section 6 |
| Design by | Structural engineer, with ground investigation |
For a piled design, yes. The engineer needs soil parameters, not assumptions.
Bored mini piles are much quieter than driven piles and are the domestic norm.
No. Excavation within 3 m of a neighbouring structure is notifiable regardless of foundation type.



Pick a slot that suits you. No obligation and no sales pressure, just straight answers on your planning route.