You apply the same way as for any householder scheme: drawings of what was actually built, the form and the £548 fee, submitted through the Planning Portal. Section 73A lets the council grant permission for work already done. The risk is that a refusal leaves you facing enforcement, so the drawings must be accurate first time.
Checked against legislation.gov.uk, GOV.UK planning guidance and MHCLG statistics on 12 September 2026. Applies to England.
It lets a council grant planning permission for development carried out before the application was made, and lets that permission take effect from the date the work was done.
Section 73A of the Town and Country Planning Act 1990 covers three situations: work carried out with no permission at all, work that outlived a temporary permission, and work that ignored a condition attached to a permission you did have. It is the route for anything that went past permitted development: a single-storey rear extension deeper than 3 metres on a terraced or semi-detached house, for example, or works in an area where an Article 4 direction removed the rights. A rear extension built with clear glazing where the permission required obscure glass, or a flat roof used as a terrace where a condition forbade it, is a breach just as much as a building nobody applied for.
A retrospective application is judged against the same Local Plan policies as any other. Government guidance is explicit that it must be considered in the normal way, on its planning merits, even where the council invited it. For the plain definition and how the term is used, see our glossary entry on retrospective planning. This guide is about doing it.
Survey what is there, draw it exactly as built, then submit a householder application with the ordinary fee.
| Item | Figure | What it means for you |
|---|---|---|
| Householder application fee, one house | £548 | The same fee as a prospective application (from 1 April 2026) |
| Lawful Development Certificate, proposed works | £274 | Half the full fee. A certificate for existing work is a different application with its own fee |
| Householder decisions in England, year to March 2026 | 151,900 | 51% of all planning decisions |
| Householder applications granted | 90% | Across all householder decisions, not retrospective ones alone |
| Decided within 8 weeks or agreed time | 93% | The usual decision window |
Sources: MHCLG, Planning fees: annual indexation from 1 April 2026; MHCLG, Planning applications in England: January to March 2026. Both retrieved 12 September 2026.
The 90% grant rate is a national figure for all householder applications. MHCLG does not publish a separate rate for retrospective ones, so treat it as the ceiling, not your odds.
In England, ten years for building work substantially completed on or after 25 April 2024. Work completed before that date keeps the old four-year limit.
The Levelling-up and Regeneration Act 2023 changed section 171B of the 1990 Act. Before the change, building operations became immune from enforcement four years after substantial completion. Now the period is ten years for everything in England. The transitional rule in regulation 5 of SI 2024/452 keeps the four-year limit for operations substantially completed, and changes of use to a single house that happened, before 25 April 2024.
| Breach | Before 25 April 2024 | On or after 25 April 2024 |
|---|---|---|
| Building work (extensions, dormers, outbuildings) | 4 years from substantial completion | 10 years from substantial completion |
| Change of use to a single dwelling | 4 years from the breach | 10 years from the breach |
| Any other breach, including breach of condition | 10 years | 10 years |
| Deliberately concealed work | The limit can be overridden: the council can apply to a magistrates' court for a planning enforcement order within 6 months of having enough evidence | |
Sources: Town and Country Planning Act 1990, s.171B; SI 2024/452, regulation 5; GOV.UK, Enforcement and post-permission matters. Retrieved 12 September 2026.
If your work is already past its limit, a retrospective application is the wrong tool. A Lawful Development Certificate for an existing development asks the council to confirm the work is immune. It turns on dated evidence: invoices, building control completion certificates, dated photographs, council tax records.
You get one chance to obtain permission after the event, and a refusal tells the council exactly what is there.
You can appeal. For a householder refusal the Planning Inspectorate must receive the appeal within 12 weeks of the decision date, cut to 28 days where an enforcement notice on the same development was served within the two years before your application. Appeals on applications made on or after 1 April 2026 follow the written "part 1" procedure: no new evidence, so the drawings you submitted are the drawings the inspector judges. Our planning appeal service sets out the fees and published timings.
The council may instead, or as well, serve an enforcement notice. That starts its own clock, explained in our guide to receiving a planning enforcement notice.
Apply once a neighbour has complained, the council has written to you, or you are about to sell. A planning contravention notice has to be answered within 21 days, and failing to reply is itself an offence under section 171D. An enforcement warning notice under section 172ZA, introduced on 25 April 2024, is the council formally inviting an application by a set date. There is no appeal against it, and it counts as enforcement action for the time limits.
Waiting in the hope of reaching immunity means ten years for anything finished since 25 April 2024, and every one of those years is a sale or remortgage where the question can come up.
No. A section 73A application is an application for planning permission and pays the ordinary fee: £548 for a householder scheme on a single house in England from 1 April 2026.
Making an application does not suspend the council's enforcement powers, so whether it waits for the decision is the council's call. Using what is built is lower risk than carrying on with unfinished unauthorised work, which a temporary stop notice can halt immediately.
The offence in section 179 of the Town and Country Planning Act 1990 is failing to comply with an enforcement notice once the compliance period has ended. A conviction carries an unlimited fine.
If building work was substantially completed before 25 April 2024, the old four-year limit still applies. Evidence of that date can support a Lawful Development Certificate instead of a retrospective application.
Yes. A householder refusal can be appealed to the Planning Inspectorate within 12 weeks of the decision date, or 28 days if an enforcement notice was served first.
Every rule on this page comes from primary legislation or government guidance, read on 12 September 2026. Your borough's Local Plan decides whether the work itself is acceptable: