Section 172 · The clock is running

Received a planning enforcement notice? What to do next

Find the date the notice takes effect. Any appeal must reach the Planning Inspectorate before that date, and the council must have served the notice at least 28 days earlier. Use those weeks to choose: comply, appeal on one of seven grounds, or apply for permission if you still can. Doing nothing ends in a criminal offence.

Checked against legislation.gov.uk, GOV.UK guidance and Planning Inspectorate statistics on 12 September 2026. Applies to England.

Which notice have you actually been served?

Six notices commonly come from a planning enforcement team, and of the six only the enforcement notice carries a right of appeal to the Planning Inspectorate.

Letters from a council enforcement team get called "an enforcement notice" whatever they are. Check the heading on the document and the section of the Town and Country Planning Act 1990 it cites, because each one runs to a different timetable. For what the term means in general, our glossary has a short entry on the enforcement notice. This guide is about responding to one.

Notice (section)What it doesDeadlineIssued in England, Jan–Mar 2026
Planning contravention notice (s.171C)Asks questions before the council decides what to doReply within 21 days; not replying is an offence1,411
Enforcement warning notice (s.172ZA)Invites a retrospective application by a set dateThe date in the notice; no appeal10
Enforcement notice (s.172)Requires steps to remedy the breachAppeal before the effective date1,435
Breach of condition notice (s.187A)Requires compliance with a condition on a permissionThe period in the notice180
Stop notice (s.183)Stops activity ahead of an enforcement noticeNormally effective 3 to 28 days after service; no appeal18
Temporary stop notice (s.171E)Stops activity immediatelyLasts up to 56 days in England73

Sources: Town and Country Planning Act 1990 (sections as listed); GOV.UK, Enforcement and post-permission matters; MHCLG, Planning applications in England: January to March 2026 (district-level authorities). Retrieved 12 September 2026.

Put the counts in proportion: in the same quarter councils decided 33,500 applications for householder development and granted 91% of them. Enforcement notices numbered 1,435, about one for every 23 householder decisions, and the power to issue one is discretionary: the council has to judge action expedient.

What is the response timeline?

Everything counts from the effective date printed on the notice. Your appeal must arrive before it, not on it.

StageRuleSource
Notice issuedThe council dates the notices.172
Notice servedNo more than 28 days after issues.172(3)(a)
Effective dateAt least 28 days after services.172(3)(b)
Appeal deadlineReceived by the Planning Inspectorate before the effective dates.174(3)
During an appealThe notice has no effect until the appeal is decided or withdrawns.175(4)
Compliance periodThe period the notice specifies for each step or activitys.173(9)
After the compliance periodOwner in breach commits an offence; unlimited fines.179

Sources: s.172, s.174, s.175 and s.179, Town and Country Planning Act 1990; GOV.UK, Appeal against an enforcement notice. Retrieved 12 September 2026.

The 28 days is a minimum, and the post can eat into it. Write the effective date on the calendar the day the envelope arrives, and plan to submit the appeal online at least a week before it.

Can you appeal, and on what grounds?

Yes, if you own, rent or lawfully occupy the land. Section 174(2) sets out seven grounds, and you can rely on more than one.

  • (a) Planning permission ought to be granted, or the condition ought to be discharged.
  • (b) The things alleged have not happened.
  • (c) They happened, but are not a breach of planning control, for example because they were permitted development and no Article 4 direction had removed those rights.
  • (d) It was too late for the council to act when the notice was issued.
  • (e) The notice was not served on everyone it should have been.
  • (f) The steps required go further than needed to remedy the breach.
  • (g) The time given to comply is too short.

Ground (a) comes with two catches. First, it carries a fee for the deemed planning application: twice the normal fee, so £1,096 for a householder scheme on one house at the £548 rate in force from 1 April 2026. It is refunded if the appeal succeeds on grounds (b) to (f). Second, since 25 April 2024 you cannot use ground (a) at all if the notice was issued after you made a related planning application, unless more than two years have passed since that application stopped being under consideration. Government guidance puts it simply: you get one attempt at permission after the event.

Ground (d) turns on the time limits in section 171B: four years for building work substantially completed before 25 April 2024, ten years for work completed since. Ground (c) is where accurate measured drawings earn their keep, because permitted development limits are dimensional, such as 3 metres of depth for a single-storey rear extension on a terraced or semi-detached house, and an inspector will check them. Ground (a) is argued against the borough's Local Plan, like any application.

Sources: Town and Country Planning Act 1990, s.174; Planning fees regulations 2012, regulation 10; MHCLG, Planning fees from 1 April 2026. The £1,096 figure is our arithmetic from those two sources. Retrieved 12 September 2026.

How long does an enforcement appeal take?

Much longer than a planning appeal. Enforcement appeals decided by written representations in June 2026 took a median of 67 weeks from being validated.

Appeal type, decided June 2026Median weeksMean weeksDecisions
Enforcement, written representations6770230
Enforcement, hearings30*28*17*
Enforcement, inquiries35*31*4*
Householder planning appeals, for comparison1214351

* Fewer than 20 decisions; the Inspectorate warns these averages are unreliable. Enforcement figures include lawful development certificate and listed building enforcement appeals. Source: Planning Inspectorate, Appeals: average timescales (updated 30 July 2026). Across the 12 months to June 2026 the Inspectorate made 3,060 enforcement decisions: statistical release, 30 July 2026. Retrieved 12 September 2026.

A long appeal is not free time. Section 175(4) suspends the notice, but anything you build in the meantime is more to remove if you lose. If the breach is an extension you live with, the wait is tolerable. If it is a half-built roof terrace, weatherproof it and stop.

What if you decide not to appeal?

Then you comply within the period stated in the notice, which can mean taking down part or all of the work. You can also ask the council, before the effective date, whether it would accept a smaller scheme: section 173A lets it vary or withdraw a notice. Section 173(11) helps here: once you comply with a notice that asked for less than it could have, planning permission is treated as granted for what remains.

Ignoring the notice is the worst option. After the compliance period the owner commits an offence under section 179, the fine is unlimited, and the court must consider the financial benefit of the breach. Councils can also enter the land, do the work themselves under section 178 and recover the cost, and after a conviction apply for a confiscation order under the Proceeds of Crime Act 2002.

What should London homeowners do this week?

  1. Write down the issue date, service date and effective date.
  2. Check the council's planning history for your address, including any refused application for the same work.
  3. Collect dated evidence of when the work was finished, if time limits might help.
  4. Get the building measured, so any appeal or fresh application is drawn from fact.
  5. Decide between appeal, compliance and a revised scheme with at least two weeks in hand.

If an appeal is the answer, our planning appeal service prepares the case and drawings. If the council has not yet issued a notice, read how to apply for retrospective planning first, because that route closes once a notice is issued.

Written by Benyamen Shaukat, Technical Architect & Platform Founder. Fact-checked against the Town and Country Planning Act 1990 (ss.171B–179) and Planning Inspectorate statistics on 12 September 2026.

Common questions

Is there a fee to appeal an enforcement notice?

There is no fee to appeal. If you appeal on ground (a), that planning permission should be granted, a fee for the deemed planning application is payable to the council at twice the normal application fee.

Can I get more time to appeal?

No. Section 174 of the Town and Country Planning Act 1990 requires the appeal to reach the Planning Inspectorate before the date the notice takes effect. A late appeal cannot be accepted, so submit well before that date.

Do I have to comply while my appeal is running?

No. Under section 175(4) the enforcement notice has no effect until the appeal is finally decided or withdrawn. A stop notice is different: it cannot be appealed to the Planning Inspectorate and exists to stop activity before the enforcement notice bites.

Will the enforcement notice show up when I sell?

Expect it to. Councils must keep a public register of enforcement and stop notices under section 188, and a buyer's solicitor can check it.

What is the penalty for ignoring an enforcement notice?

Once the compliance period has ended with no appeal outstanding, the owner commits an offence. The fine is unlimited, and the court must take into account any financial benefit gained from the breach.

Where to go next

The law behind an enforcement notice

Enforcement is discretionary: the council must be satisfied there is a breach and that action is expedient, having regard to the development plan. The statutory rules are these: